Acceptance testing a coding line: what to measure, and what to refuse

Contract 12 min read Published 26 Nov 2026 Sources: standards, field reports
The short answer

Acceptance is not a try-out after delivery. It is a written definition of "this machine works", agreed before the order — because the moment the machine lands, the definition gets written by whoever is standing next to the line at two in the morning.

Why this gets skipped

Three pressures push acceptance testing to the end, and all three are understandable:

The cheapest hour in the whole project

One hour spent writing pass criteria before the order is worth more than a week of argument after installation. It costs nothing, and it converts a conversation about opinions into a conversation about measurements.

FAT and SAT are different jobs

FAT — factory acceptanceSAT — site acceptance
WhereSupplier's plant, before shipmentYour line, after installation
What it provesThe machine meets specification as builtThe machine works in your process, with your product, your operators, your air and power
MaterialYour own substrate, sent in advance — not their sampleProduction material from the actual line
SpeedAt specified minimum and maximumAt the speed you will really run, including ramp-up and stop-start
Who signsYour engineer, remotely or on siteProduction, quality and maintenance together
If it failsCheap to fix — the machine has not shippedExpensive to fix — the line is stopped and the invoice is due

If you can only insist on one, insist on FAT with your own material. Problems found there cost days; the same problems found at SAT cost weeks and a negotiation.

Two gates, factory acceptance before shipment and site acceptance after installation, with the cost of a failure rising between them
Figure 1. The test is the same at both gates. What changes is who pays when it fails — and by the second gate the line is already stopped.

The test sheet

Four groups. Every row has a pass criterion you can measure — not "acceptable", not "good", but a number or a yes/no.

1 · Mark quality

TestHow to run itPass criterion (set your own)
Dry rub Firm pressure with a dry cotton cloth, 20 strokes, same spot No visible loss of legibility at reading distance
Solvent wipe 70% IPA on a cloth, 10 wipes — repeat with the solvent your process actually uses Mark still legible; no transfer to the cloth after the third wipe
Tape pull Pressure-sensitive tape applied over the mark, pressed, then pulled at 90° No more than minor ink transfer; code still decodes
2D code grade Verify with a calibrated verifier, not a phone app Grade ≥ C (1.5) is a common purchasing requirement; check what your customer or regulator asks for
Contrast Measured on the same verifier, on the darkest and lightest product you run Meets the grade above on both — this is where dark compounds fail

2 · Speed and stability

TestHow to run itPass criterion
1,000-code run Print 1,000 consecutive codes at production speed without intervention Missing or unreadable characters in fewer than an agreed number of codes — a fraction of a percent, written down
Minimum speed Run at the slowest speed the line will ever use Code quality unchanged; no smearing or double-print
Shift-length run One full shift without stopping to clean or adjust No operator intervention required, or a documented interval at which one is
Stop-start 20 stops and restarts, as the line really behaves First code after each restart is correct — this catches lost position and purge waste

3 · Data and function

TestHow to run itPass criterion
Metre mark accuracy Measure a 100 m run against the printed counter; repeat at low and high speed Deviation within the tolerance your product standard requires, consistently at both speeds
Date rollover Force a date and lot change, including a month end Rolls without manual intervention; no duplicate or skipped date
Product changeover Time a switch from one product or code format to another Under the agreed minutes, done by a trained operator unaided
Alarms Trigger low ink, low solvent, blocked filter, open guard Each produces a distinct alarm the operator can act on — no generic "fault"
Access control Try to change a parameter as an operator, not an engineer Restricted as specified, with changes logged

4 · Site conditions

TestHow to run itPass criterion
Daily cleaningTime a full routine clean by an operatorUnder the agreed minutes, with the machine back in production
Consumable changeChange ink, solvent or ribbon with production waitingUnder the agreed minutes, no spill, no restart error
Power and airMeasure actual draw and consumption at the machineWithin the figures in the specification you signed
Extraction and fumeRun the worst-case product and observe at the operator positionNo perceptible fume or dust at the operator position
NoiseMeasure at the operator position during productionWithin the site limit stated in your own risk assessment

Set your own numbers in the right-hand column before the order. A criterion added after installation is a preference, not a requirement.

Copy the blank test sheet

CODING LINE ACCEPTANCE — FAT / SAT Site: Date: Signed by: MARK QUALITY Dry rub 20 strokes pass/fail ____ Solvent wipe 10x (70% IPA) pass/fail ____ Tape pull 90 deg pass/fail ____ 2D grade (verifier) measured ____ min ____ Contrast, darkest product measured ____ SPEED & STABILITY 1,000 code run defects ____ max ____ Minimum line speed pass/fail ____ Full shift, no intervention pass/fail ____ 20 stop-starts pass/fail ____ DATA & FUNCTION Metre accuracy @ 100 m error ____ tol ____ Date / lot rollover pass/fail ____ Changeover time minutes ____ max ____ Alarms (ink/solvent/filter) pass/fail ____ Parameter access control pass/fail ____ SITE Daily clean time minutes ____ max ____ Consumable change time minutes ____ max ____ Power / air draw measured ____ Fume at operator position pass/fail ____ Noise at operator position dB ____ max ____

Five things that pass and still fail

What happenedWhy it passedWhat it costs later
Tested on the supplier's sample material Their sample is chosen to work Adhesion or contrast fails on your actual compound
Only tested at the nominal speed Nominal is the best case Missing characters appear at the speed you actually run during peaks
Tested for an hour An hour is not a shift Printhead drying, ink settling and filter loading all appear later
Nobody timed the cleaning Cleaning is "the operator's job" Twenty extra minutes per shift is a permanent, unbudgeted labour cost
No product changeover test It was set up for one product Every subsequent changeover takes twice as long and needs an engineer

What to put in the contract

Four clauses do most of the work. They are short, and none of them is unusual — a supplier who resists them is telling you something.

01

A pass criterion per line, in the annex

Attach the test sheet as an annex. "Meets specification" is not a criterion; "fewer than 3 defective codes in 1,000 at 250 m/min" is.

02

Payment split at acceptance

A meaningful final payment released on signed SAT. Ten percent is enough to make the conversation happen; without it, the conversation is optional for the supplier.

03

A remedy window, with a date

If SAT fails, a defined period to correct it, and what happens if it is missed — including the right to reject. Undefined remedies are the same as none.

04

Consumables price and third-party permission

Unit price, escalation, minimum volume, and whether third-party consumables are allowed. This is the clause that decides years four and five, and it is almost never in the first draft.

Questions we get

Can I insist on FAT if the machine is a standard model?

Yes, and it is easier than for a custom build — the supplier only has to run your material through a machine that already exists. Offer to send material and attend remotely. A refusal usually means the material is the problem, which is precisely what you wanted to find out before shipping.

What code grade should I demand for 2D codes?

Grade C (1.5) measured with a calibrated verifier is a common purchasing floor; some customers and regulated markets require B or better. The number matters less than agreeing it in writing and measuring it on the worst product you run, not the best.

How long should the stability run be?

One full shift, at production speed, with no intervention. An hour hides printhead drying, ink settling and filter loading — the three things that make a machine feel unreliable in month two.

Do I need a verifier, or will a phone app do?

For acceptance, you need a calibrated verifier if the code is a data carrier. Phone apps read codes; they do not grade them against a standard, so they cannot give you a number to put in a contract.

What if the supplier's engineer disagrees with my result?

This is why the criterion goes in the annex with the method beside it — 20 strokes, 10 wipes, 1,000 codes. Two people following the same written method can compare results; two people arguing about "looks fine" cannot.